Progress Billing & Milestone Billing
How a quote's lines track what is left to bill, and where milestone invoices stand today
One quote, many invoices: bill in stages without re-keying the order.
Progress billing invoices a job in parts as the work advances, instead of all at the end. Milestone billing is the same idea tied to agreed checkpoints, such as 30% on kickoff, 40% at the halfway point and the balance on delivery. In Laureo both rest on the same figure: each billable line already tracks its remaining to bill, so the figures always reconcile back to what the customer agreed to. No page raises a milestone invoice yet: on the quote page you convert the whole quote into one invoice.
Every billable line carries a remaining to bill figure: the part of that line not yet invoiced. Converting the quote draws the whole remaining amount at once. A milestone invoice draws part of it, and the line's remaining figure goes down by exactly that much. Once every line is fully drawn, the order is fully billed and there is nothing left to invoice.
The quote as a whole is also never billed past its total. An invoice you void, or credit back in full with credit notes, stops counting toward that total. If it was a milestone invoice, the amount it drew also goes back onto the lines it drew from, so that work can be billed again in a new milestone. If you converted the whole quote at once and then credited that invoice, the quote can be billed again here in milestones. A partial credit still counts in full and gives nothing back, because it does not say which part of the work it unbilled.
Reversing a credit that had closed a milestone invoice puts the drawn amount back on that invoice too. If the same work has been billed on another invoice in the meantime, the reversal is refused, so nothing is billed twice: void or fully credit the newer invoice first, then reverse the credit.